Miscellaneous Page of the Cost Data Wizard

Use this page to configure various custom field values that will be loaded during export.

Note: This page displays only if you select DOE PARS on the Project and Format page.

Cost

Use this group box to set the options for the Cost file.

Field Description
EVT Justification Use this field to select a note category to justify the earned value technique used on the work package.
The JSON file is populated with a value only for the following progress techniques:
  • User Defined
  • Planning Package
  • Assignment % Complete
  • Calculated Apportionment
  • Steps
  • Earned as Spent
  • % Complete Manual Entry

This field is required.

IPMR Header

Use this group box to set the options for the IPMR file.

Field Description
Quantitative Risk Analysis Confidence Level (Cost) This field defaults to 0. You may enter a value from 0 to 100 in this field.
Quantitative Risk Analysis Confidence Level (Schedule) This field defaults to 0. You may enter a value from 0 to 100 in this field.
Undistributed Budget (Work Days) Use this field to enter the number of calendar days representing the Undistributed Budget, the budget applicable to the contract effort that is not yet distributed to the WBS elements at or below the reporting level.

This field defaults to 0. You may enter numerical or decimal values in this field.

Undistributed Budget for EAC (Work Days) Use this field to enter the number of calendar days of the EAC for the Undistributed Budget.

This field defaults to 0. You may enter numerical values in this field.

Escalation Rate Use this field to enter the anticipated project escalation rate.

This field defaults to 0.00. You may enter numerical, decimal, or negative values in this field.

EAC Best Case Date Use this field to enter or select the EAC best case date.
EAC Most Likely Date Use this field to enter or select the EAC most likely date.
EAC Worst Case Date Use this field to enter or select the EAC worst case date.